Project Status
Action C1 - Existing prototype optimization and definitive design of the product (July 2018 - June 2019)
0%
Action C2 - Flammability risk assessment (April 2019 - June 2020)
0%
Action C3 - Design and installation of the required production facilities at INNOVA and manufacturing of DD-AC R290 pre-series (April 2019 - June 2021)
0%
Action C4 - Validation of DD-AC R290 and In-Field Testing (January 2020 - June 2021)
0%
Action C5 - Replicability and transferability (July 2020 - June 2021)
0%
Action D1 - Monitoring the impact of the ZEROGWP project (July 2018 - June 2021)
0%
Action E1 - Dissemination planning and execution (July 2018 - June 2021)
0%
Action F1 - Project management by INNOVA (July 2018 - June 2021)
0%
Completed Deliverables
Dissemination and Outreach Plan
LCA goal and scope
Partnership Agreement
Progress report on dissemination and networking activities
Report on the prototype performance test protocols
Website
Report on flammability risks in double duct air conditioners upon field-tests
Designs and constructive specifications of the DD industrial air conditioner working with R290 refrigerant
External laboratory certifications
Design schemes of new refrigerant charge station and components
Product safety test report
Technical report on performance results and comparison with other systems
LCA inventory
Performance indicators database (mid-term report)
Guidelines for numerical simulation of flammable refrigerant diffusion in rooms
Early systems of dual duct AC pre-series with R290 refrigerant
Technical data sheet for DD-AC R290 (construction drawings, batch, manuals, test reports, separate industrial costs)
Mounting cycles and quality specifications
Final report on field tests
After-LIFE plan
Business Plan
Environmental Product Declaration (EPD) of the double duct system with R-290
Final report on dissemination and networking activities
Layman’s report
Performance indicators database (final report)
Performance test protocols for DD-AC R290 subjected to field tests
Product Category Rules (PCR) for air conditioners
Report on participation to standardization committees
Report on replication and transfer potential of HC refrigerants
Socio-economic impact of the project actions on the local economy and population
Milestones reached
Kick-off workshop event
Project website is operating
Kick-Off Meeting
Partnership Agreement signed by all partners
Networking with relevant stakeholders and other projects
Verification of laboratory performance compliance
• Upgrade of the new refrigerant charge station complete and assembly line operating
Assessment of flammability risks in double duct air conditioners
Technical and financial reports ready to be submitted for mid-term payment request
Workshop on environmental and safety issues on the use of HC refrigerants
Feedbacks from CEN meetings
Verification of installation progresses after 8 months (summer season) and problems encountered if any
Verification of installation progresses after 14 months (winter season) and problems encountered if any
Availability of preliminary LCA results, evaluation of indicators, updating data
Availability of final LCA results
High-quality data and information for BP elaboration. Consensus meeting on exploitable results
Verification of installation progresses after 14 months (winter season) and problems encountered if any
Consolidated draft version of technical and financial reports for final payment request
Final conference
Final version of Performance indicators (KPI) LIFE Webtool
Project results shared with CEN TC182 Committee